Sequences of actions (PEV Generic Interface v2)

Controller starts-up

When powering up Advantics controller, the operating system starts-up, then a few application processes start. The main controller process is the first one to start, and will immediately start emitting its messages every 100 ms (1s for the controller inputs feedback message).

At the beginning it reports a state of Initialising in signal EVSE_Information.Communication_Stage until all internal processes started-up and are talking to each other.

Afterwards, EVSE_Information.Communication_Stage reports a state of Waiting_For_EVSE.

ChargerAdvantics ControllerCustomer VCUChargerAdvantics ControllerCustomer VCUInitialisation[User] Power onSystem boot-up~15 seconds[0x600] EVSE_Information.Communication_Stage == InitialisingWait for charger[0x600] EVSE_Information.Communication_Stage == Waiting_For_EVSE

Charge initialisation

Once a pistol is plugged in, a so-called charge session is initialised. It allows for exchange of ATTENTION parameters between vehicle and charger, such as voltage, current and power limits. In CCS it can take a few tens of seconds, especially if payment authorisation is carried on.

Note

Upon detection of a plug-in, the controller IO configured as Plugged_In will be set to HIGH state. For instance, on ADM-CS-EVCC controller, DIG_OUT1 IO is configured by default for this particular function. Refer to /srv/config.cfg file for more details.

EVSE_Information.Communication_Stage reports a state of Negotiating_Connection at first. During this exchange of parameters, EVSE_Information message will also update its other signals with information it got from the charger. Within that time, the only piece of information customer VCU needs to provide is the present battery state of charge. It should do so by sending EV_Information message early on.
In addition to the EV_Information message, the customer VCU can provide the following optional messages: EV_V2X_Energy_Request, EV_Extra_BPT_Information, EV_Energy_Request. If EV_Energy_Request is not emitted, the Advantics PEV controller will use the values from the /srv/config.cfg file. These three messages can be emitted at any time to update the values.

Once done with the negotiation, EVSE_Information.Communication_Stage reports Connected_With_Full_Info. Advantics controller will also activate the inlet lock, such that charge pistol cannot be pulled-out from that moment.

Attention

Advantics controller will NOT proceed with the rest of the sequence until inlet lock reports a locked state. As there are different styles of lock feedback, it is IMPORTANT to properly configure the controller for the right type of lock used in the inlet port.

ChargerChargerAdvantics ControllerAdvantics ControllerCustomer VCUCustomer VCUChargerAdvantics ControllerCustomer VCUCharge initialisation[User] Plug-inPlugged_In IO goes to HIGH state[0x600] EVSE_Information.Communication_Stage == Negotiating_Connectionloop[Exchange of information][0x600] EVSE_Information.Protocol == ...[0x600] EVSE_Information.Pins == ...[0x600] EVSE_Information.Max_Current == ...[0x610] EV_Information.State_of_Charge == ...[0x614] EV_Energy_Request == (Target_Energy_Request = XX,(Optional signals in [0x614] EV_Energy_Request) Maximum_Energy_Request = XXX, Minimum_Energy_Request = X)(Optional) [0x615] EV_V2X_Energy_Request == ...(Optional) [0x616] EV_Extra_BPT_Information == ...Connected with full info[0x600] EVSE_Information.Communication_Stage == Connected_With_Full_InfoCheckInlet lock

Determining between AC charging and DC charging

Advantics controller supports both types of charge, and the generic CAN interface reflects that. In order to differentiate between an AC charge and a DC charge, two ways are provided. One could be regarded as informational, the other one as imperative.

Attention

You will see that the generic interface does not mix up Control and Status messages between AC and DC charging. Each type of charge use its own set of dedicated messages. Other messages common to both types of charge are labeled Information and do not truly participate in the sequence of actions required to make one of these charge type works.

Note

While the generic interface provides a CCS_Extra_Information message, it should NOT be regarded as a way to implement charge sequences on your side. The Advantics controller is already doing that for you, including all kinds of protocol and safety checks! These are literally meant as Extra information.

The informational way is by looking at EVSE_Information.Pins signal. It will contain which pins of the inlet will be energised as soon as that information is definitely known. As combo inlet ports use separate pins for AC and DC, this can be seen as a discriminant factor.

The imperative way is to listen to AC_Control and DC_Control messages. Their signals will be used only at the right moment.

AC Charging

In case of AC charging, when Connected_With_Full_Info state is reached, EVSE_Information.Pins will contain one of the value valid for AC charging (ie. the corresponding label starts with "CCS_AC"). EVSE_Information.Max_Current will also contain valid information that has been either detected from the cable rating (PP resistance), charger CP PWM duty cycle, or negotiated during CCS High Level Communication.

Getting to charge

As soon as the charger send us it is ready to do AC charging, AC_Control.Ready_To_Deliver_Power is set to Ready.

Note

This flag being set to Ready does NOT mean voltage is present on AC pins yet! It just means EVSE is in position of delivering power. Before EVSE close its relays, it is waiting on vehicle to signal it also wants power.

When the vehicle on-board charger is ready to take power in, set AC_Status.Ready_To_Charge to Ready. Charger will close its AC relays. Only then can on-board charger proceed to draw current. Advantics controller will then emit a state of Charging in EVSE_Information.Communication_Stage.

Tip

You can have AC_Status.Ready_To_Charge always set to Ready, even before a charge session starts. Like so, Advantics controller will go to Charging state, and power will be available as soon as possible. In all cases, Advantics controller will NOT signal vehicle readiness (ie. CP State C) to charger before the inlet lock confirmed its locked state. Therefore, it is safe and fine for customer VCU to be eager to signal it is Ready for AC charging (even from Waiting_For_EVSE state, and even if the charge session ends up being a DC charge).

During charging, you only have to regularly update EV_Information.State_of_Charge.

Attention

During charging you should not exceed current limit provided in EVSE_Information.Max_Current. Be aware that charger can also change its maximum current during charging!

Charger-initiated end of charge

When EVSE wants to stop charging, it is signaled by AC_Control.Ready_To_Deliver_Power set to Not_Ready. EVSE_Information.Communication_Stage will also go to Ending_Charge state. On-board charger should stop drawing current within 3 seconds. Only then you should set AC_Status.Ready_To_Charge to Not_Ready. EVSE_Information.Communication_Stage will then go to state Closing_Communication, and Advantics controller waits 100ms for charger to open its AC relays before unlocking the pistol from the inlet port.

Vehicle-initiated end of charge

When EV wants to stop charging, on-board charger should stop drawing current. Only then you should set AC_Status.Ready_To_Charge to Not_Ready (unless this is an emergency stop, in which case you are allowed to set it to Not_Ready irrespective of when the on-board charger stops its current draw).

EVSE_Information.Communication_Stage will then go to state Ending_Charge. When charger confirmed it is no longer ready to deliver power, EVSE_Information.Communication_Stage will go to state Closing_Communication, and Advantics controller waits 100ms for charger to open its AC relays before unlocking the pistol from the inlet port.

Charge termination and restart

As soon as pistol is plugged out, IO configured as Plugged_In is set to LOW state, all signals of all messages are re-initialised, and EVSE_Information.Communication_Stage goes back to Waiting_For_EVSE.

If pistol is still plugged in, charger can also decide to restart a charge. In which case, EVSE_Information.Communication_Stage goes to Connected_With_Full_Info state directly, inlet is locked again, and the process can repeat.

ChargerChargerAdvantics ControllerAdvantics ControllerCustomer VCUCustomer VCUOn-board chargerOn-board chargerChargerAdvantics ControllerCustomer VCUOn-board chargerAC: Start of charge[0x600] EVSE_Information.Communication_Stage == Connected_With_Full_Info[0x600] EVSE_Information.Pins == CCS_AC*[0x600] EVSE_Information.Max_Current == ...AC: Charger is readyReady[0x601] AC_Control.Ready_To_Deliver_Power == ReadyAC: Vehicle is readyInternal checks[0x611] AC_Status.Ready_To_Charge == ReadyReadyCloses AC relaysAC: Chargingloop[Charging]Applies voltage on AC pins[0x600] EVSE_Information.Communication_Stage == ChargingCharge(max_current=...)Draws current
ChargerChargerChargerChargerChargerChargerAdvantics ControllerAdvantics ControllerAdvantics ControllerAdvantics ControllerAdvantics ControllerAdvantics ControllerCustomer VCUCustomer VCUCustomer VCUCustomer VCUCustomer VCUCustomer VCUOn-board chargerOn-board chargerOn-board chargerOn-board chargerOn-board chargerOn-board chargerChargerAdvantics ControllerCustomer VCUOn-board chargerAC: Charger-initiated end-of-chargeNot ready[0x601] AC_Control.Ready_To_Deliver_Power == Not_Ready[0x600] EVSE_Information.Communication_Stage == Ending_ChargeStop chargeStops currentdrawStopped[0x611] AC_Status.Ready_To_Charge == Not_ReadyNot ready[0x600] EVSE_Information.Communication_Stage == Closing_CommunicationOpens AC relaysInlet unlockAC: Vehicle-initiated end-of chargeStop chargeStops currentdrawStopped[0x611] AC_Status.Ready_To_Charge == Not_ReadyNot ready[0x600] EVSE_Information.Communication_Stage == Ending_ChargeOpens AC relaysInlet unlockNot ready[0x600] EVSE_Information.Communication_Stage == Closing_CommunicationAC: Terminating charge session[User] Unplug[0x600] EVSE_Information.Communication_Stage == Waiting_For_EVSE

DC Charging

In case of DC charging, when Connected_With_Full_Info state is reached, EVSE_Information.Pins will contain one of the value valid for DC charging (ie. the corresponding label starts with "CCS_DC"). EVSE_Information.Max_Current will also contain valid information that has been negotiated during CCS High Level Communication.

Note

CP duty cycle and PP resistance do NOT play a part in determining maximum current during a DC charge.

Insulation test

Insulation test is a step meant to verify the charging cable is not damaged in a way it could be a safety hazard for the user. It consists in charger applying a test voltage (normally, the maximum and riskier voltage that charger would be applying across a whole charge, typically 500 V). It then measures the output current and deduce the insulation resistance.

By electrical safety standards, the insulation resistance should be of at least 100 Ohms/V. For a 500 V test voltage that means an insulation resistance >= 50 kOhms.

Inlet lock should be activated by now. Therefore, Advantics controller gives its permit to charger to apply power. EVSE_Information.Communication_Stage goes to Insulation_Test state. Vehicle only has to wait as this step is fully happening on charger side.

Attention

Charger will apply high voltage on inlet DC pins during that step. This voltage should not go beyond DC contactors.

When charger is done and reports no insulation error or malfunction, the charging process can continue to next step.

ChargerChargerAdvantics ControllerAdvantics ControllerCustomer VCUCustomer VCUDC ContactorsDC ContactorsChargerAdvantics ControllerCustomer VCUDC ContactorsDC: Insulation testStart insulation test[0x600] EVSE_Information.Communication_Stage == Insulation_Testloop[Insulation test]Applies high voltageChecksTest statusContinue testVoltage goes to 0 VTest done

Precharge

When vehicle closes its DC contactors, battery voltage is applied up to charger power electronics output which should be at a potential close to 0 V right after insulation test. This can create arcing in vehicle contactors if some current is allowed to flow, and severely deteriorate them.

To handle this situation, CCS adopted the precharge process, which consists in having charger matches battery voltage prior to vehicle closing its DC contactors.

When EVSE_Information.Communication_Stage goes to Precharge state, Advantics controller will frequently probe charger with precharge requests, setting as target voltage the voltage provided in DC_Status2.Battery_Voltage.

Advantics controller then waits that DC_Status2.Inlet_Voltage matches DC_Status2.Battery_Voltage to ± 20 V. Once reached, DC_Control.Close_Contactors is emitted with value Close. It then waits that DC_Status2.Contactors_Closed is set to Close as well before continuing to the next step.

Tip

Advantics controller can also support certain CAN sensors measuring battery voltage, inlet voltage and flowing current. This can be configured in /srv/config.cfg. If you use one of those, then you will not need to provide valid values for DC_Status2.Battery_Voltage and DC_Status2.Inlet_Voltage.

Tip

Advantics controller can also support driving contactors directly with its own H-Bridge outputs and feedback input. This can be configured in /srv/config.cfg. If you use the controller IOs to drive contactors, you do not need to provide feedback on DC_Status2.Contactors_Closed. For your information, DC_Control.Close_Contactors will still be emitted when it closes the contactors by itself though.

ChargerChargerAdvantics ControllerAdvantics ControllerCustomer VCUCustomer VCUDC ContactorsDC ContactorsChargerAdvantics ControllerCustomer VCUDC ContactorsDC: Precharge[0x613] DC_Status2.Battery_Voltage == XXXStart precharge with target == XXX[0x600] EVSE_Information.Communication_Stage == Prechargeloop[Waiting for matching voltages]Applies voltage[0x613] DC_Status2.Battery_Voltage == XXX[0x613] DC_Status2.Inlet_Voltage == XXXPresent output voltage == XXXCheck voltages:Battery voltage > 20 Vabs(Inlet voltage - Battery voltage) <= 20 VPrecharge continue with target == XXXPresent output voltage == XXX[0x602] DC_Control.Close_Contactors == CloseUse controller IOs to drive contactorsPrecharge continue with target == XXXCloses[0x613] DC_Status2.Contactors_Closed == CloseUse controller IOs to get contactors feedbackPresent output voltage == XXX

Waiting for Charge

Advantics controller makes a small transition through Waiting_For_Charge state in EVSE_Information.Communication_Stage. This is matching CCS initial PowerDelivery request/response. You don't have too much to do here. Just keep refreshing DC_Status1, DC_Status2 and EV_Information.

ChargerAdvantics ControllerCustomer VCUBMSChargerAdvantics ControllerCustomer VCUBMSDC: Start of chargeWaiting for charge[0x600] EVSE_Information.Communication_Stage == Waiting_For_ChargeCharging modeCurrent request[0x612] DC_Status1(Max_Charge_Current=XXX, Present_Current=X, Max_Discharge_Current=XX)[0x613] DC_Status2[0x610] EV_Information[0x614] EV_Energy_Request == (Target_Energy_Request = XX,(Optional signals in [0x614] EV_Energy_Request) Maximum_Energy_Request = XXX, Minimum_Energy_Request = X)(Optional) [0x615] EV_V2X_Energy_Request == ...(Optional) [0x616] EV_Extra_BPT_Information == ...Waiting, ready

Unidirectional Power Transfer (normal charging)

At this stage the actual charging loop starts. The process is very simple: you send current requests to Advantics controller using the signal Max_Charge_Current, which forward them to charger, which forward them to power modules. Power modules deliver power into the battery. From voltage, current and temperature readouts we check everything is fine. Rinse and repeat.

You should send regularly DC_Status1, DC_Status2 and EV_Information (it is actually a good idea to always send them, and not wait for some controller states explicitly needing them).

Target voltage sent to charger is the one defined as target_voltage entry in the config file. This value is not meant to change as charging a battery is a Continuous Current process. Ie. power modules from charger only control their output current. Voltage is "controlled" by the battery chemistry itself. And BMS role is to regulate the amount of current requested to charger in function of the present battery voltage. Note that target voltage is limited by charger negotiated maximum voltage.

Advantics controller will overwrite BMS current request with various static and dynamic limits. In any case, current request that is send to charger can never be above BMS current request.

Current request limits, in order applied:

  • max_current entry in config file [static]
  • Charger negotiated maximum current [dynamic]
  • max_power entry in config file, divided by present battery voltage [dynamic]
  • Charger negotiated maximum power, divided by present battery voltage [dynamic]
  • Temperature sensors configured current derating curve (as a proportional modifier) [dynamic]
  • Ramp-up rate limit (see current_ramp entry in config file, default to 20 A/s) [dynamic]

Advantics controller will stop charging in following conditions:

  • DC contactors feedback (through CAN or controller IO) says they are open
  • If max_charge_voltage entry is defined in config file and present battery voltage is greater or equal to this value
  • If max_soc entry is defined in config file, and EV_Information.State_of_Charge is greater or equal to this value
  • Advantics controller IO for charge stop is activated
  • DC_Status2.Normal_End_of_Charge is set to Stop_Requested
  • A temperature sensor reached a configured stop threshold value
  • Inlet voltage has more than 20 V deviation from battery voltage
  • Amount of current flowing is deviating too far from requested setpoint (configurable in config file)

Tip

As during precharge, if you use a supported CAN sensor to measure battery and inlet voltage,

and controller IO to drive contactors, you do not need to send DC_Status2.

Note

See also No code mode section for special mode requiring no message to be sent from you to reach a working charge.

ChargerAdvantics ControllerCustomer VCUBMSChargerAdvantics ControllerCustomer VCUBMSDC: ChargingCharge at Target Voltage and Current Request[0x600] EVSE_Information.Communication_Stage == Chargingloop[Waiting for any stop conditions]Current request[0x612] DC_Status1(Max_Charge_Current=XX, Present_Current=X, Max_Discharge_Current=0)[0x613] DC_Status2[0x610] EV_InformationPresent voltage and currentCapping current request to various limitsCharge at Target Voltage and Current Request

Power Transfer with ISO 15118-20

ISO 15118-20 supports 2 control modes: the scheduled mode and the dynamic mode.

What separates Scheduled Mode from Dynamic Mode is who decides the setpoint:

Dynamic mode Scheduled mode
Who chooses the power and the direction The charger, freely, within the limits you publish The vehicle, on every DC_ChargeLoopReq
What the vehicle sends each loop Limits and energy requests — a range A setpoint, plus limits
What the charger contributes decides the setpoints within the agreed range based on factors like (electricity price, grid needs, OCPP/CSMS, etc.) A schedule for the power transfer agreed apon with the vehicle once, up front, which then gets followed

Power Transfer - Dynamic Mode

With the support of ISO 15118-20, bidirectional power transfer became possible through the dynamic modes defined by the protocol. In Dynamic control mode, besides the static power transfer parameters, vehicle provides the Energy requests and the range for bidirectional cycling (V2X energy requests).

It is possible to specify the absolute energy requests including the range for bidirectional cycling (V2X energy requests) within the battery capacity limit. Based on these parameters and the state of charge of the battery we will then dynamically calculate relative energy requests and V2X cycling range limits and forward them to the charger.

In addition, the vehicle will be able to specify the time of departure which can be used in dynamic mode.

Optionally, all these parameters can be dynamically updated using the following CAN message: EV_V2X_Energy_Request, EV_Extra_BPT_Information, EV_Energy_Request. If EV_Energy_Request

Then the actual power transfer loop starts. The process is very simple: you send current requests to Advantics controller using the signals Max_Charge_Current and Max_Discharge_Current, which forwards them to the charger.

The charger in the dynamic mode has the liberty to cycle between charging and discharging the vehicle's battery within the provided limits depending on the application, as long as the target energy request of the vehicle is reached by the departure time. The power transfer direction and the power setpoints are determined by a third-party system, such as a Central System Management System (CSMS) via OCPP or a local control system on the charger. This decision-making process considers factors like real-time electricity pricing and grid requirements.

The vehicle can limit the charger to only one direction of power transfer (charge only or discharge only) by defining the Max_Charge_Current and Max_Discharge_Current CAN signals accordingly.

You should send regularly DC_Status1, DC_Status2 and EV_Information (it is actually a good idea to always send them, and not wait for some controller states explicitly needing them).

Target voltage sent to charger is the one defined as target_voltage entry in the config file. This value is not meant to change as charging a battery is a Continuous Current process. Ie. power modules from charger only control their output current. Voltage is "controlled" by the battery chemistry itself. And BMS role is to regulate the amount of current requested to charger in function of the present battery voltage. Note that target voltage is limited by charger negotiated maximum voltage.

The BMS current request can be used in this case as the Max_Charge_Current limits.

When the config entry dynamic_current_limit is false, the current limits will defined by:

  • max_current entry in config file [static]
  • max_discharge_current entry in config file [static]
  • Charger negotiated maximum current [dynamic]
  • max_power entry in config file, divided by present battery voltage [dynamic]
  • max_discharge_power entry in config file, divided by present battery voltage [dynamic]
  • Charger negotiated maximum power, divided by present battery voltage [dynamic]
  • Temperature sensors configured current derating curve (as a proportional modifier) [dynamic]
  • Ramp-up rate limit (see current_ramp entry in config file, default to 20 A/s) [dynamic]

When the config entry dynamic_current_limit is true, the current limits capped by the charger's:

  • negotiated maximum current [dynamic]
  • max_power entry in config file, divided by present battery voltage [dynamic]
  • max_discharge_power entry in config file, divided by present battery voltage [dynamic]
  • negotiated maximum power, divided by present battery voltage [dynamic]

Advantics controller will stop charging in following conditions:

  • DC contactors feedback (through CAN or controller IO) says they are open
  • If max_charge_voltage entry is defined in config file and present battery voltage is greater or equal to this value
  • If max_soc entry is defined in config file, and EV_Information.State_of_Charge is greater or equal to this value
  • Advantics controller IO for charge stop is activated
  • DC_Status2.Normal_End_of_Charge is set to Stop_Requested
  • DC_Status2.Emergency_Stop is set to Emergency_Stop_Requested
  • A temperature sensor reached a configured stop threshold value
  • Inlet voltage has more than 20 V deviation from battery voltage
  • Amount of current flowing is deviating too far from requested setpoint (configurable in config file)

Tip

As during precharge, if you use a supported CAN sensor to measure battery and inlet voltage,

and controller IO to drive contactors, you do not need to send DC_Status2.

Note

See also No code mode section for special mode requiring no message to be sent from you to reach a working charge.

ChargerAdvantics ControllerCustomer VCUBMSChargerAdvantics ControllerCustomer VCUBMSDC: Bidirectional Power Transfer - Dynamic ModeCharge at Target Voltage and Current Request[0x600] EVSE_Information.Communication_Stage == Chargingloop[Waiting for any stop conditions]Current Limits[0x612] DC_Status1(Max_Charge_Current=XXX, Present_Current=X, Max_Discharge_Current=XX)[0x613] DC_Status2[0x610] EV_Information[0x614] EV_Energy_Request == (Target_Energy_Request = XX,(Optional signals in [0x614] EV_Energy_Request) Maximum_Energy_Request = XXX, Minimum_Energy_Request = X)(Optional) [0x615] EV_V2X_Energy_Request == ...(Optional) [0x616] EV_Extra_BPT_Information == ...Present voltage and currentCapping current requests to various limitsCharge at Target Voltage and respect Current Limits

Power Transfer - Scheduled Mode

Scheduled mode is the other control mode ISO 15118-20 defines.

Ask for it by setting preferred_control_mode = Scheduled in the [ccs] section of the configuration file. Everything else on this page — the insulation test, precharge, the stop conditions, the limits the controller applies — behaves as described for the other modes.

It is a preference, not a demand

A charger advertises one or more parameter sets, each with a control mode and a connector type. The controller selects the first set whose connector matches yours and whose control mode matches your preference. If the charger offers no set with your preferred mode, the controller falls back to the first compatible set and the session runs in the other mode rather than failing. The outcome is logged at service selection as Selected <mode> control mode (preferred was <mode>).

Controlling voltage or current, never both

[V2G20-2183] requires the vehicle to provide either EVTargetVoltage or EVTargetCurrent in a DC_ChargeLoopReq, never both. Which one you control is selected with EV_Status.ISO15118_Part20_Scheduled_Mode_Control:

Value EVTargetCurrent EVTargetVoltage
Current_Control (default) DC_Status1.Max_Charge_Current 0 V -- the max voltage is used as target
Voltage_Control 0 A -- the max current is used as target DC_Status1.Target_Voltage, or target_voltage from the config file

The signal can be changed at any point during a session, and resets to Current_Control whenever EVSE_Information.Communication_Stage cycles back to Waiting_For_EVSE.

Current control is the usual choice, for the same reason as in unidirectional charging: charging a battery is a constant-current process, the charger's power modules regulate current, and the voltage follows the battery chemistry. Voltage control exists for the cases where you want the charger to hold a voltage instead — a constant-voltage phase, for example.

In a unidirectional session the target current is clamped to be non-negative; in a BPT session it may be negative, which is how discharge is requested. When the vehicle asks for a normal stop, the controller requests 0 A.

What the vehicle sends in the charge loop

Alongside the setpoint, every request carries the envelope the charger must stay inside:

  • EVMaximumChargePower, EVMinimumChargePower
  • EVMaximumChargeCurrent
  • EVMaximumVoltage, EVMinimumVoltage

and in a bidirectional session also:

  • EVMaximumDischargePower, EVMinimumDischargePower
  • EVMaximumDischargeCurrent

These come from the same configuration entries and CAN signals as in the other modes, so the current and power capping rules described under Dynamic Mode apply unchanged.

Current deviation is measured differently

The current deviation check means something different in the two modes, because the vehicle asks for something different:

Mode What is compared
Scheduled Present current against the setpoint the controller last requested
Dynamic How far present current falls outside the advertised range [-max_discharge_current, max_charge_current]

In both cases the deviation has to persist for current_deviation_t before the charge is stopped, and current_deviation_accept_less still suppresses the error when the charger delivers less than asked.

Relevant config entries

End of charge and terminating charge session

This sequence comes at the end of a charge, when the charge has not been aborted irregularly. Advantics controller makes a small transition through Ending_Charge state in EVSE_Information.Communication_Stage.

It then goes to Welding_Detection state, during which it waits for current to lower below 1 A before opening contactors. It then waits for inlet voltage to lower below 60 V before unlocking the pistol.

When the charge session is over, Advantics controller emits a Closing_Communication state until pistol is unplugged. As soon as pistol is plugged out, IO configured as Plugged_In is set to LOW state, all signals of all messages are re-initialised, and EVSE_Information.Communication_Stage goes back to Waiting_For_EVSE.

ChargerChargerChargerAdvantics ControllerAdvantics ControllerAdvantics ControllerCustomer VCUCustomer VCUCustomer VCUDC ContactorsDC ContactorsDC ContactorsChargerAdvantics ControllerCustomer VCUDC ContactorsDC: End of chargeStopping charge[0x600] EVSE_Information.Communication_Stage == Ending_ChargeDC: Contactors welding detectionWelding detection[0x600] EVSE_Information.Communication_Stage == Welding_Detectionloop[Waiting for current to lower]Present voltage == XXX[0x612] DC_Status1.Present_Current == XXXCheck flowing current <= 1 AWelding detection continue[0x602] DC_Control.Close_Contactors == OpenController IOs stop driving contactorsOpens[0x613] DC_Status2.Contactors_Closed == OpenUse controller IOs to get contactors feedbackloop[Waiting for voltage to lower]Present voltage == XXX[0x613] DC_Status2.Inlet_Voltage == XXXCheck inlet voltage <= 60 VWelding detection continueInlet unlockDC: Terminating charge sessionCharge session finished[0x600] EVSE_Information.Communication_Stage == Closing_Communication[User] Unplug